SafeSetter, LLC

    262-745-3849

Savings along with Production

CHICAGO

Fly Over Bridge in Illinois savings and production:

Without SafeSetter:

296 overhang bridge brackets

10 days to hang brackets at 8 hours a day (all double time night hours for carpenters and OT night hours for laborers)

2 Man lifts

4 Carpenters

2 Laborers

4 Lane closures

Misc fuel

Break down:

2 Man lifts $600 a day= $6000

4 Carpenters $400 per hour (remember double time) at 8 hours a night for 10 days= $32,000

2 Laborers $105 per hour (remember OT nightly wage)= $8400

4 Lane closures at $3800 per lane= $15,200

Misc fuel for 10 days=$1000

Total Cost $62,600

SafeSetter Way:

296 Brackets

24.5 hours to hang

1 Carpenter

1 Laborer

1 Carpenter at night over CTA

1 Laborer at night over CTA

No lane closures! Approved by DOT engineers to go over live traffic and CTA. (Companies discretion to have approved to go over live traffic)

Break Down:

1 Carpenter at $50 per hour for 23 hours =$1150

1 Laborer at $35 per hour for 23 hours= $805

1 Carpenter at $100 per hour for 1.5 hours=$150

(remember night hours over CTA)

1 Laborer at $52.50 per hour for 1.5 hours=$78.75

(remember night hours over CTA)

NO man lift, NO fuel, NO Lane Closures

Total Cost: $2183.75

Company saved $60,416.25

These savings are based on hanging overhang bridge brackets. There are more savings that trickle down when you speed up production and take a safer and more ergonomic approach.

2018 Patented device for hanging overhang bridge brackets..SafeSetter, LLC. is not affiliated with any construction supply company or distributor